Steel structure of the K2 and K3 lines

An important stage of work on the two new thermal waste processing lines at ZUSOK in Warsaw is behind us. We already have 70% of the support structure for the new boilers, which has reached its full height of 37 meters. In recent days we have installed, among other things, the 20-meter high side walls of the first line of boilers. We carried out the operation of installing the feed water tank for the boilers. This was a complicated task due to the location and dimensions of the tank (length: 12.3 m, cross-section: 3.85 m, weight: 18.2 t). In parallel,…