We have started the installation of the flue gas cleaning system. Three silos have already been placed at their destinations, and we are waiting for the delivery of the last one – the silo no 4. The operation of transporting, unloading, lifting (by two cranes) and setting on the support structure is a logistically and technically advanced process, especially since intensive work is underway at the site. A single silo is 18 meters long and weighs 13 tons. Each had to be moved over the heat treatment hall to reach the installation point.