The project at the halfway point

Work at ZUSOK has reached the halfway point, and we are carrying out many important operations in parallel. The most important in recent weeks has been the completion of the turboset, which consists of the turbine, generator, gearbox and other equipment. The last component, i.e. the generator, arrived at the construction site and was placed on the foundation.  Construction of the chimney shaft has been completed, finishing assembly work is underway. On the flyover leading to the unloading hall, reinforced concrete work and prestressing of the structure have been completed. We are continuing the assembly of the boiler steel structure…